The following is a Gantt Chart. A Gantt Chart is a chart in which series of horizontal lines shows the amount of work done or production completed in certain periods of time in relation to the amount planned for those period. Below, is a screen capture of my gantt chart and the progress I plan to make each week.
Deliverable
|
Approx. Date
|
Project
Week
|
Project start
|
Jan 16th
|
1
|
Project Blog
|
Ongoing
|
1-14
|
Project Proposal
|
Jan 25th
|
2
|
Research Report
|
Feb 3rd
|
3
|
Wire Frame/navigation structure moodboard
|
Feb 10th
|
4
|
User
Requirements (Wire Frame/user testing/profiling) Interface Design
|
Feb 20th-24th
|
6
|
Presentation
of first prototype – mandatory attendance,
marked, full class present
|
March 6th -10th
|
8
|
Testing week
|
March 27th- 31st
|
11
|
Final Report
|
April 3rd to 7thth
|
12
|
Easter holidays
|
2 weeks
|
|
Week of Demonstration
|
April
24th to 28th
|
13
|